File #: ACT 24-014    Version: 1 Name:
Type: Acceptance Status: Agenda Ready
File created: 4/2/2024 In control: City Council
On agenda: 4/16/2024 Final action:
Title: Consideration of and action on accepting completion of the Rehabilitation of the 13th Street Lift Station.
Sponsors: Public Works
Attachments: 1. 13th - Affidavit of Bills Paid and Warranty
Requester: Public Works
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Title

Consideration of and action on accepting completion of the Rehabilitation of the 13th Street Lift Station.

 

Body

Summary: 

In October, the Public Works Department requested to purchase, through the Buy Board, the services of Fuquay, Inc. to rehabilitate the 13th Street Lift Station. This project consisted of bypass pumping, cleaning and debris removal from inside the wet well, grouting of structural damage, and lining of surface of the wet well with an epoxy lining system for the lift station.    

 

Fiscal/Budgetary Impact:

The contract amount and total cost of the work performed is $691,508.01.

Funding for this project was covered out of Water & Sewer Bond funds 508, and 509 as well as the Wastewater Treatment Plant’s budget 400-502-49030.

 

Recommended action

Accept completion and release retainage for this project.