Title
Accept completion of the Golf Course Cart Path Renovations from SKE Construction, LLC via Buyboard contract number 660-21.
Body
Summary:
On 06/04/2024, City Council approved the purchase of services from SKE Constrruction, via the Buyboard contract 660-21, to correct several issues with the cart paths at the Battleground Golf Course.
The quoted price was 60,168.77 to complete the renovations to the cart path. The final, lump sum, cost was $60,168.77.
Attached are the closeout documents for this project.
Fiscal/Budgetary Impact:
Funds for this project were allocated in 10-850-49030:
$100,000.00 Budgeted amount for the project (10-850-49030)
$ 60,168.77 Project Cost
$ 39.831.23 Amount remaining from budgeted amount
Recommended action
Accept completion of the Golf Course Cart Path Renovations from SKE Construction, LLC via Buyboard contract number 660-21.