File #: ACT 25-014    Version: 1 Name:
Type: Acceptance Status: Agenda Ready
File created: 3/5/2025 In control: City Council
On agenda: 3/18/2025 Final action:
Title: Consideration of and action on accepting completion of the Battleground Golf Course Cart Path Renovations.
Attachments: 1. Change order No. 1 - Cart Path Renovation, 2. Letter of Completion, 3. Consent of Surety to Final Payment, 4. Waiver of Lien Affidavit and 1 year warranty, 5. Pay App- Deer Park Golf Course
Requester: Parks & Recreation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Title

Consideration of and action on accepting completion of the Battleground Golf Course Cart Path Renovations.

 

Body

Summary: 

On December 17, 2024 City Council approved the purchase of services from SKE Construction, through Buy Board Contract #660-21, to perform the Battleground Golf Course Cart Path Renovations.  The contracted amount was $83,305.00.  A change order in the amount of an additional $9,470.00 was issued, due to additional work needed at hole #11. 

All work has been completed at a total cost of $92,821.35.  At this time, we are ready to have City Council accept completion of the project.

 

Fiscal/Budgetary Impact: 

Funds for this project were budgeted in 010-850-49030.

 

Recommended action

Accept completion of the Battleground Golf Course Cart Path Renovations.