Title
Consideration of and action on accepting completion of the Battleground Golf Course Cart Path Renovations.
Body
Summary:
On December 17, 2024 City Council approved the purchase of services from SKE Construction, through Buy Board Contract #660-21, to perform the Battleground Golf Course Cart Path Renovations. The contracted amount was $83,305.00. A change order in the amount of an additional $9,470.00 was issued, due to additional work needed at hole #11.
All work has been completed at a total cost of $92,821.35. At this time, we are ready to have City Council accept completion of the project.
Fiscal/Budgetary Impact:
Funds for this project were budgeted in 010-850-49030.
Recommended action
Accept completion of the Battleground Golf Course Cart Path Renovations.