Consideration of and action on amending the original agreement with Studio Red for design services for the theater/court building.

 

Body

Summary: 

The Studio RED team will provide additional architectural, structural, civil, and MEP Design Services based

on the findings in the Facilities Assessment Report dated July 23, 2026.

•                     Demolition of old existing HVAC equipment. This will open up areas and increase interior usable

square footage.

•                     New roof mounted HVAC equipment (improve zone control/comfort, consolidate units, improve

operations/maintenance, downsize units where loads have been reduced due to owner changing

incandescent fixtures to LED).

•                     Replace all existing supply, return, and exhaust ductwork.

•                     Replace existing chilled water lines.

•                     Study and upgrade roof structure if required to support new mechanical equipment.

•                     Fully sprinkle the building.

•                     Replace bus weathered, existing electrical gear, and wiring as required based on age and industry

standards.

•                     Modify existing electrical to support new mechanical equipment.

•                     Since we are removing a lot of the ceilings to replace ductwork and add sprinklers the owner may choose to have the design team replace old lighting fixtures with new.

 

 

Fiscal/Budgetary Impact: 

Original amount of $244,840.00. is being increased by $200,250.00. for a total contract amount of $445,090.00.

 

Recommended action

Approve to amend the original agreement with Studio Red for design services for the theater/court building to add an additional $200,250.00 due to change in scope.