Title: Accept completion of the Sanitary Rehabilitation of Oklahoma Ave., New Orleans St., Tulsa St., and Atlanta St. in the Deer Meadows Subdivision Section 2.
Sponsors: Public Works
Attachments: 1. Letter of Completion, 2. Final Pay App for Retainage
Requester: Public Works
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Title

Accept completion of the Sanitary Rehabilitation of Oklahoma Ave., New Orleans St., Tulsa St., and Atlanta St. in the Deer Meadows Subdivision Section 2.

 

Body

Summary: 

The Sanitary Rehabilitation of Oklahoma Ave., New Orleans St., Tulsa St., and Atlanta St. in the Deer Meadows Subdivision Section 2 has been completed and staff is ready to release retainage on the project.  The work was performed by Vortex Services.

The project consisted of pipe bursting 8-inch sanitary pipe on Oklahoma Ave., New Orleans St., Tulsa St., and Atlanta St. and rehabilitation of 15 manholes. The original Buy Board contract price was $565,676.00.  The actual cost of the project was $498,277.96, which is a savings of $67,398.04.    

 

Fiscal/Budgetary Impact: 

This project was funded through the CIP Water/Sewer (Fund 513).

 

Recommended action

Staff recommends accepting completion of the project and releasing the $24,903.90 currently being held in retainage.