Consideration of and action on accepting completion of Library Plumbing Rehabilitation.
Body
Summary:
The Library Plumbing Rehabilitation Project was awarded to Blackmon, Inc. on 08/4/26 in in the amount of $154,500.00. The work has been completed by the contractor and inspected by our inhouse inspectors. The project is now ready for Council to accept final completion.
Fiscal/Budgetary Impact:
Funding for this project was budgeted in the library’s operational budget.
Recommended action
Accept completion of the Library Plumbing Rehabilitation Project completed by Blackmon, Inc.