Title: Consideration of and action on accepting completion of the Center Street Waterline Improvements by SKE Construction via Buy Board contract #660-21.
Sponsors: Public Works
Attachments: 1. Letter of Completion - Center Street, 2. Change Order No 1 - Center Street Waterline
Requester: Public Works

Title

Consideration of and action on accepting completion of the Center Street Waterline Improvements by SKE Construction via Buy Board contract #660-21.

 

Body

Summary: 

An emergency repair was made to replace 480 feet of 8” pipe at the intersection of Center Street and Forest Street. The original repair cost was $84,621.15.  However, it was necessary to issue a change order in the amount of $11,950.00 making the total repair cost $96,571.15.   The additional cost is due to a valve that could not be isolated which required a bypass, an extra 6-inch and 8-inch wet connection and a 6-inch insertion valve.  The work has now been completed and we are ready for Council to accept completion and approve releasing retainage.

 

Fiscal/Budgetary Impact: 

Funding for this project was covered Certificates of Obligation bonds funds (fund 511).

 

Recommended action

Accept completion of the Center Street Waterline Improvement and approve releasing retainage.