Title: Consideration of and action on amending the original agreement with Studio Red for design services for the theater/court building.
Attachments: 1. Architects - Amendment No. 1 - Sept 2026

Title

Consideration of and action on amending the original agreement with Studio Red for design services for the theater/court building.

 

Body

Summary: 

The Studio RED team will provide additional architectural, structural, civil, and MEP Design Services based

on the findings in the Facilities Assessment Report dated July 23, 2026.

                     Demolition of old existing HVAC equipment. This will open up areas and increase interior usable

square footage.

                     New roof mounted HVAC equipment (improve zone control/comfort, consolidate units, improve

operations/maintenance, downsize units where loads have been reduced due to owner changing

incandescent fixtures to LED).

                     Replace all existing supply, return, and exhaust ductwork.

                     Replace existing chilled water lines.

                     Study and upgrade roof structure if required to support new mechanical equipment.

                     Fully sprinkle the building.

                     Replace bus weathered, existing electrical gear, and wiring as required based on age and industry

standards.

                     Modify existing electrical to support new mechanical equipment.

                     Since we are removing a lot of the ceilings to replace ductwork and add sprinklers the owner may choose to have the design team replace old lighting fixtures with new.

 

 

Fiscal/Budgetary Impact: 

Original amount of $244,840.00. is being increased by $200,250.00. for a total contract amount of $445,090.00.

 

Recommended action

Approve to amend the original agreement with Studio Red for design services for the theater/court building to add an additional $200,250.00 due to change in scope.