Title: Consideration of and action on accepting completion of the 10-Inch Waterline Improvements on Center Street.
Sponsors: Public Works
Attachments: 1. Conditional Waiver and Release of Final Payment, 2. Conditional Waiver and Release on Progress Payment
Requester: Public Works

Title

Consideration of and action on accepting completion of the 10-Inch Waterline Improvements on Center Street. 

 

Body

Summary: 

At the April 7, 2026 meeting, City Council approved purchasing the services of Branch Construction to perform the 10-Inch Waterline Improvements on Center Street Project.  This purchase was made through their TIPS contract #23010401. The project involved replacing 2,200 linear feet of old 10-inch asbestos concrete waterline with new 10-inch HDPE pipe between P Street and San Augustine on Center Street.

The contract amount was $428,909.00.  The project has been completed with the final cost being $428,909.00.

 

Fiscal/Budgetary Impact: 

This project was funded out of various water/sewer bonds.

 