Title

Consideration of and action on purchasing the services of SKE Construction to replace 350 linear feet of waterline on Phyllis Street (Buy Board contract #660-21).

 

Body

Summary: 

The 2-inch waterline main on Phyllis Street broke 4 times in a week.  Repairs were made each time the mainline broke, however it is just a matter of time before it breaks again.  The Water & Sewer Maintenance Supervisor recommends that we replace 350-linear feet of 2-inch cast-iron waterline with 4-inch HDPE pipe.

SKE Construction is a Buy Board vendor (#660-21) and has provided a quote of $52,007.62 for this waterline replacement.  

 

Fiscal/Budgetary Impact: 

This is not a budgeted waterline replacement, however we have remaining funds in the Series 2018 C/O, water/sewer bond funds (Fund 511).  A portion of these remaining funds were recently used for the waterline replacement on Boston and Center Street and we are proposing to use this same fund for the $52,007.62 to replace the waterline on Phyllis. 

 

Recommended action

Approve the purchase of service from SKE Construction for the waterline replacement.