Skip to main content
File #: AGR 18-021    Version: 1 Name:
Type: Agreement Status: Agenda Ready
File created: 7/26/2018 In control: City Council
On agenda: 8/7/2018 Final action:
Title: Consideration of and action on entering into an agreement for engineering services for the Rehabilitation of the P Street Ground Storage Tank.
Sponsors: Public Works
Attachments: 1. Dunham Engineering Agreement
Requester: Public Works
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Title

Consideration of and action on entering into an agreement for engineering services for the Rehabilitation of the P Street Ground Storage Tank.

Body

Summary:  Staff is requesting to enter into an agreement with Dunham Engineering for the rehabilitation of the P Street one million gallon water ground storage tank.  Dunham Engineering will prepare the design, engineering plans and specifications for this project.  They will also perform inspection of the actual rehabilitation project once the project has been awarded to a contractor.   The estimated cost for the rehabilitation project is $570,000. 

The agreement with Dunham Engineering is for a proposed engineering cost of $65,000 which breaks down as follows:

                     Phase I - Design

                                          Total Fee of $50,000

                     Phase II - Construction oversight and inspection

                                          Total Fee of $15,000

 

Fiscal/Budgetary Impact:  This project is being funded out of Series 2017-A Certificates of Obligation Bond (Fund 52)

 

Recommended action

Staff recommends entering into an agreement with Dunham Engineering for a cost of $65,000 for their services on this project.