Legislation Details

File #: ACT 26-035    Version: 1 Name:
Type: Acceptance Status: Agenda Ready
File created: 6/9/2026 In control: City Council
On agenda: 6/16/2026 Final action:
Title: Consideration of and action on acceptance of the completion of and release of retainage for the Spencerview Bridge Project by Lucas Construction.
Attachments: 1. Final Pay Estimate_Signed

Title

Consideration of and action on acceptance of the completion of and release of retainage for the Spencerview Bridge Project by Lucas Construction.

 

Body

Summary: 

The Spencerview Bridge Project consisted of the construction of new sidewalks, installation of a new bridge from Glenwood Park to Spencerview Athletic Complex, and final grade work.

All final scope of the project has been completed and it has been inspected by the Registered Accessibility Specialist (RAS).

The project is ready for Council acceptance and for the release of the retainage of $20,006.15.

 

Fiscal/Budgetary Impact: 

The approved budget for this project funded through the Community Development Corporation.  The awarded bid was $421,650.54. The final payment for the project and release of retainage is $20,006.15

 

Recommended action

Accept the project completion, and release retainage in the amount of $20,006.15 for the Spencerview Bridge Project completed by Lucas Construction.