Title
Acceptance of completion and retainage release of the CMP Rehabilitation on Jefferson Ave. Project.
Body
Summary:
This project consisted of UV Lining 2050 LF of large diameter Storm drainage pipe on Jefferson Ave. The services for this Project were purchased through the Buy Board Cooperative Purchasing Program using Fuquay, Inc. The total price for this project is $656,721.86. The retainage to be released on this project is $65,672.19. The project has been completed and is ready for council acceptance
Fiscal/Budgetary Impact: This project is funded through 2019 CIP Fund 90
Recommended action: Staff Council accept completion of the project