Skip to main content
File #: ACT 18-033    Version: 1 Name:
Type: Acceptance Status: Agenda Ready
File created: 9/10/2018 In control: City Council
On agenda: 10/2/2018 Final action:
Title: Acceptance of completion and retainage release for the Deer Park Nature Preserve Phase I Project.
Sponsors: Parks & Recreation
Attachments: 1. Nature Preserve Payment App
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Title

Acceptance of completion and retainage release for the Deer Park Nature Preserve Phase I Project.

 

Body Summary: 

Millis Development & Construction, LLC has completed the Deer Park Nature Preserve Project and is now ready for Council acceptance and retainage release. The original contract amount was $554,809.00. The project had a Change Order in the amount of $8,431.70. This brings the total cost of the project to $563,240.70. The Project included the completion of the Deer Park Nature Preserve Phase I Project which included nature trails, parking, lighting, grading, landscaping, monument installation and signage. This will complete all items related to the Deer Park Nature Preserve Phase I Project.

 

Fiscal/Budgetary Impact: 

This project was funded through bond money.

Retainage                     $56,324.07

 

Recommended action

Staff is requesting acceptance of the project and release of retainage.