Accept completion of the Traffic Signal Rehabilitation at Pasadena Blvd & Havana St.
Body
Summary: At the December 19, 2023 City Council awarded the Traffic Signal Rehabilitation at the intersection of Pasadena Blvd. and Havana Street to Pfeiffer and Son, LTD in the amount of $122,355.00.
The project has been completed, with the final cost being $122,355.00. We are currently withholding $12,235.50 in retainage.
Fiscal/Budgetary Impact:
Funding for this project was budgeted in the 2023-2024 fiscal year Capital Improvement Fund (090-405-49030).
Recommended action
Accept completion of this project and releasing the retainage to Pfeiffer & Sons.