Skip to main content
File #: ACT 25-010    Version: 1 Name:
Type: Acceptance Status: Agenda Ready
File created: 1/24/2025 In control: City Council
On agenda: 4/1/2025 Final action:
Title: Consideration of and action on accepting completion of the new Emergency Operations Center and Renovation to the Police Department Building.
Attachments: 1. G704-2017 - Final - Deer Park EOC Addition-signedPGAL
Requester: Police
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Title

Consideration of and action on accepting completion of the new Emergency Operations Center and Renovation to the Police Department Building.

 

Body

Summary: 

On November 11, 2022 City Council awarded the contract for the new “Emergency Operations Center and Renovations to the Police Department Building”, to Durotech, Inc. in the amount of $6,990,000.00.  During the construction period there was a net change order addition of $140,308.37 making the revised contract amount $7,130,308.37.

Construction has now been completed with the final construction cost being $7,064,750.48.

 

Fiscal/Budgetary Impact: 

The majority of this project was funded out of the Crime Control and Prevention District budget with the remainder being funded out of the city’s Capital Improvement Fund.

 

Recommended action

Accept completion of this project and approve final payment, along with the release of retainage being held. 

 

.