Title
Consideration of and action on approval of a change order on the Deer Park Terrace Street Reconstruction Project.
Body
Summary:
At the May 6, 2025 City Council meeting, Council approved amending the agreement with Schaumberg and Polk, Inc. to include additional design work to add the reconstruction of W. Fourth Street to the existing Deer Park Terrace Street Reconstruction Project. The design has been completed which will add $765,527.50 to the construction contract with Environmental Allies.
As you recall, from the May 6th meeting, W. Fourth Street has deteriorated drastically. It has been in poor shape for years. Although it is adjacent to the existing street construction currently going on, it was not included in the original scope of services. However, the road has continued to deteriorate, especially with the heavy construction trucks currently driving on it.
At this, for your consideration, is a change order adding this additional work to the project scope. This change order increases the contract amount, with Environmental Allies, from $6,348,689.00 to $7,114,216.50.
Fiscal/Budgetary Impact:
This project is being funded out of funds allocated, for both streets and drainage, in bond fund 309 (2021 General Obligation Bond).
Recommended action
Approve the change order on the Deer Park Terrace Street Reconstruction Project.