Title: Consideration of and action on acceptance of completion for the replacement of the cast iron water line on Phyllis Street.
Sponsors: Public Works
Attachments: 1. Consent to Final - 101452648 EXEC, 2. INv. 645, 3. Pay App-1-, 4. Phyllis St and Doris St Redlines, 5. Waiver of Lien, Affidavit of Bills Paid & 1 yr warranty
Requester: Public Works
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Title

Consideration of and action on acceptance of completion for the replacement of the cast iron water line on Phyllis Street.

 

Body

Summary:

The water line on Phyllis St. was constructed of cast iron. In recent years, and more recently, this had several failures. Public Works made the decision to replace the water line with HDPE, which has a life span of more than 50 years. Public Works hired SKE Construction to replace the line under emergency contract.

 

Fiscal/Budgetary Impact: 

Total cost of this replacement was $52,007.62.

 

Recommended action

Accept completion of the water line replacement on Phyllis Street.