File #: PUR 24-040    Version: 1 Name:
Type: Purchase Status: Agenda Ready
File created: 10/17/2024 In control: City Council
On agenda: 11/5/2024 Final action:
Title: Consideration of and action on approval to purchase traffic signal battery backup systems for 13 intersections via Buy Board contract # PE-05-21.
Sponsors: Public Works
Attachments: 1. Battery Backup Quote
Requester: Public Works
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Title

Consideration of and action on approval to purchase traffic signal battery backup systems for 13 intersections via Buy Board contract # PE-05-21.

 

Body

Summary: 

CenterPoint is responsible to resolve most power outages, affecting our traffic signals, in a reasonable timeframe, unless the outage is due to some type natural disaster, which could then take hours or days to have the signals placed back in service.  Last fiscal year we budgeted funds to install a battery backup system at 8 of intersections along Center Street.      

This year we have budgeted $83,000 to install the battery backup system to an additional 13 intersections. With the backup system, if power is lost the system will automatically transfer to battery power and run the intersection for 8 to 10 hours. In situations where power may be out for several days, this system would allow staff time to make the other 16 intersections safe, before turning their attention to the Center St. corridor.

The total cost to purchase the equipment from Consolidated Traffic Controls, Inc. (via Buy Board contract # PE-05-21) is $80,990.00.

 

Fiscal/Budgetary Impact: 

Funds are budgeted in the Traffic Maintenance account 010-405-49040.

 

Recommended action

Approve the purchase traffic signal battery backup systems for 13 intersections via Buy Board contract # PE-05-21.