File #: ACT 23-088    Version: 1 Name:
Type: Acceptance Status: Agenda Ready
File created: 11/22/2023 In control: City Council
On agenda: 12/5/2023 Final action:
Title: Acceptance of completion of the purchase and installation of fielding lighting for the Dow Park Baseball fields and release of final payment and retainage to Musco Sports Lighting.
Attachments: 1. Musco Retainage
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Title

Acceptance of completion of the purchase and installation of fielding lighting for the Dow Park Baseball fields and release of final payment and retainage to Musco Sports Lighting.

 

Body

Summary: 

Musco Sports Lighting has completed the delivery and installation of field lights for two (2) fields at the Dow Park Baseball Fields (Varnell and Bowyer) as part of the repairs from tornado damage and is now ready for Council acceptance and release of final payment including retainage. The project was completed in the amount of $621,629.00 which includes the cost of change orders.

The project is completed; the contract is ready to be closed out and final payment issued.  Attached is the final payment application which is the retainage of the project. Retainage amount is $31,081.45.

 

Fiscal/Budgetary Impact: 

$596,629.00                                          Musco Proposal for purchase of lights and installation

  $25,000.00                                          Change order for additional parking lot lights

 ($31,081.45)                                          Retainage to from the project

$621,629.00                                          Total project cost including retainage

 

Recommended action

Accept completion of the purchase and installation of field lighting for the Dow Park Baseball fields and release of final payment and retainage to Musco Sports Lighting.