File #: DIS 16-145    Version: 1 Name:
Type: Discussion Status: Agenda Ready
File created: 9/12/2016 In control: City Council Workshop
On agenda: 9/20/2016 Final action:
Title: Discussion of issues relating to proposal number two from CDM Smith for extended additional services on Phase I of the Wastewater Plant renovations.
Attachments: 1. Deer Park - Proposal for Amendment 2 for Additional Services (09-07-2016)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Title

Discussion of issues relating to proposal number two from CDM Smith for extended additional services on Phase I of the Wastewater Plant renovations.

Body

Summary: 

The Notice to Proceed with construction of phase one was issued on June 24, 2015 with a contractual final completion date of June 30, 2016.  Delays mostly due to weather have caused the project to extend beyond CDM Smith’s additional services allowance.  The proposal is to extend construction materials testing, resident project representative, and inspection services through the end of the project.  In order to maintain continuity through the end of the project staff recommends approval of the not to exceed proposal for $27,510.00.

 

Fiscal/Budgetary Impact: 

Water & Sewer Capital Improvement Plan, C.O. bond fund 48

Recommended action

Item on the council agenda for consideration.