File #: ACT 17-007    Version: 1 Name:
Type: Acceptance Status: Agenda Ready
File created: 1/23/2017 In control: City Council
On agenda: 2/7/2017 Final action:
Title: Acceptance of completion and release of retainage to Vaught Services for the Surface Water Treatment Plant Valve Replacement Project.
Attachments: 1. Affidavit
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Title

 

Acceptance of completion and release of retainage to Vaught Services for the Surface Water Treatment Plant Valve Replacement Project.

 

Body

Summary: 

 

 

On November 1st, 2016, the City awarded Vaught Services with the bid to perform the replacement of the valves on the high service pumps at Deer Park’s Surface Water Treatment Plant. The valves needed to be replaced due to extreme wear since being installed in the late ‘80s. Their services were purchased through The Interlocal Purchasing System (TIPS) for a total of $97,076.61.

In agreement with the contractor, the City has withheld a 5% ($4,853.83) retainage until completion of the work. The work has now been completed and staff is requesting that council accept the completion of the project and approve the release of retainage of $4,853.83 to the contractor.

 

Fiscal/Budgetary Impact: 

 

This is a budgeted item from the surface water treatment account 40-506-4904.

 

Recommended action

 

Staff is recommending that council accept the completion and release of retainage of $4,853.83 to the contractor.