Title
Acceptance of Phase I of the Wastewater Plant Renovation Project with CSA Construction.
Body
Summary:
On March 17, 2015 the city entered into a contract with CSA Construction, Inc. for phase I of the wastewater plant renovation project for $4,908,600. Our consultant, CDM Smith, has submitted the final completion document and is recommending acceptance of the project. There were four change orders on the project for $90,054.00, which resulted in a total construction cost for phase I of $4,998,654.00. Final payment to CSA Construction is for $279,652.98 and the one-year warranty period begins with council acceptance of the project.
Fiscal/Budgetary Impact:
CO Bond fund 29
Recommended action
Staff recommends council accept the phase I of the wastewater plant renovation project and issue final payment to CSA Construction for $279,652.98.