Title: Acceptance of Phase I of the Wastewater Plant Renovation Project with CSA Construction.
Attachments: 1. Cover Letters, 2. App for Paymt #16, 3. CO#4, 4. Rec for Final Pymt, 5. Contractor Release of Owner, 6. Cert of Substantial Completion, 7. Cert Final Completion
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Title

Acceptance of Phase I of the Wastewater Plant Renovation Project with CSA Construction.

Body

Summary: 

On March 17, 2015 the city entered into a contract with CSA Construction, Inc. for phase I of the wastewater plant renovation project for $4,908,600.  Our consultant, CDM Smith, has submitted the final completion document and is recommending acceptance of the project.  There were four change orders on the project for $90,054.00, which resulted in a total construction cost for phase I of $4,998,654.00.  Final payment to CSA Construction is for $279,652.98 and the one-year warranty period begins with council acceptance of the project. 

Fiscal/Budgetary Impact: 

CO Bond fund 29

Recommended action

Staff recommends council accept the phase I of the wastewater plant renovation project and issue final payment to CSA Construction for $279,652.98.