File #: ACT 17-042    Version: 1 Name:
Type: Acceptance Status: Agenda Ready
File created: 9/25/2017 In control: City Council
On agenda: 10/3/2017 Final action:
Title: Acceptance and release of retainage for completion of the SWTP - Replacement of Electrical Switchgear B.
Sponsors: Public Works
Attachments: 1. Acceptance letter and pay estimate for MCC-B
Requester: Public Works
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Title

Acceptance and release of retainage for completion of the SWTP - Replacement of Electrical Switchgear B.

Body

Summary: 

Hi-Tech Electric, Inc. has completed the SWTP - Replacement of Electrical Switchgear B project and is now ready for Council acceptance.  The original contract amount was $45,010.00, a change order in the amount of $792.00 was executed to add additional wire that was found to be needed during construction.  The final contract amount is $45,802.00.  Retainage to be released on this project totals $2,290.10.  The one year warranty will start upon Council acceptance.

Fiscal/Budgetary Impact: 

This project was funded out of the CIP

Recommended action

Staff is requesting acceptance and release of retainage