Title
Consideration of and action on change orders to the contract with South Pools for the Dow Park Pavilion Project.
Body
Summary:
The Deer Park Community Development Corporation (DPCDC) is a component unit of the City. The DPCDC budget includes funding for several parks and recreation capital projects, including the Dow Park Pavilion and Improvements project. A bid in the amount of $617,737.50 was awarded to South Pools on this project on February 21, 2017.
On June 26, 2017 a change order on the project was approved in the amount of $80,484.60.
The following change orders are now needed to complete the project:
Change order #2: $9,031.66 for labor for installation of additional piers per the design by ICON design details
Change order #3: $42,744 electrical work to complete the project.
Fiscal/Budgetary Impact:
City funds will needed to be appropriated since DPCDC funds are committed. Funds are available in the unassigned fund Balance for this expenditure. A budget amendment is included on the January 2, 2018 Regular Council Meeting Agenda for this purpose.
Recommended action
Approve the Change Orders No. 2 and 3 to the contract with South Pools for the Dow Park Pavilion Project.