Title: Approval of Balancing Change Order and acceptance of completion of the 10" Force Main replacement at HCFCD B112-00-00.
Sponsors: Public Works
Attachments: 1. aerial crossing balancing CO, 2. Aerial crossing final pay app
Requester: Public Works
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Title

Approval of Balancing Change Order and acceptance of completion of the 10” Force Main replacement at HCFCD B112-00-00.

Body

Summary: PMG, LLC has completed the 10” Force Main replacement at HCFCD B112-00-00.  A deduct balancing change order in the amount of $47,703.00 brings the contract from the awarded contract amount of $99,166.00 to a completed contract amount of $51,463.00. Approval of this project includes the retainage release in the amount of $2,573.15.  This project was completed under budget and on time.

 

Fiscal/Budgetary Impact: 

This project was funded out of the Water/Sewer Contingency Fund

Recommended action

Staff is requesting approval of the Balancing Change Order and acceptance of the completed project