Title
Consideration of and action on accepting the amendment for additional professional services from Halff Associates Task Order No 16-004-E.
Body
Additional services for the structural overlay for the existing tectum roof deck to accommodate a new roofing attachment satisfying current wind ratings.
Fiscal/Budgetary Impact
May 9, 2015 the citizens in Deer Park passed a special election Type B Economic Development Sales and Use Tax for the appropriation of $2,000,000 for the renovations of the Maxwell Adult Center.
$2,000,000.00 Appropriated funds for the Maxwell Adult Center Project
Approved by DPCDC & Council
$1,562,000.00 Lowest Responsible Bidder - Frost Construction
$283,300.00 Professional Services - Halff Associates
$1,845,300.00 Total Contract Amount
Approved by DPCDC & Council (Unencumbered Contingency)
$154,700.00 Total in Unencumbered Contingency
$ 48,684.97 Change Order #1 - Demo Services, Waterproofing, Applied Services
Change Order #2 - Installation of new foundation piers and replace floor $19,265.95 slab
Amendment for additional professional services from Halff Associates
$7,468.78 Task Order No 16-004-C
Amendment for additional professional services from Halff Associates
Task Order No 16-004-D (Page 1 of this task order has been replaced
$6,765.00 since last approved to reflect the correct task order number)
$72,515.30 Remaining Total in Unencumbered Contingency
Requesting from Unencumbered Contingency
$72,515.30 Remaining Total in Unencumbered Contingency
Amendment for additional professional services from Halff Associates
$6,600.00 Task Order No 16-004-E
$65,915.30 Estimated Remaining Total in Unencumbered Contingency
Recommended Action
Accept the amendment for additional professional services from Halff Associates Task Order No 16-004-E