Consideration of and action on a purchase of services from Fuquay, Inc., through the Buy Board Cooperative Purchasing Program to perform CMP Rehabilitation - Basin 3.
Body
Summary:
Consideration and action on the purchase of services from Fuquay, Inc. through the Buy Board to perform CMP Rehabilitation throughout the City. An inspection was conducted by Fuquay identifying Corrugated Metal Pipe that was damaged throughout the City’s storm outfall system that need to be repaired and rehabilitated using an UV liner system and Epoxy Liner. This system prevents further damage and strengthens the existing pipe preventing failure and prolongs the length of the life of the system. The project consists of 4,100 LFT of liner to be installed. The cost of this project is $352,355.54.
Fiscal/Budgetary Impact:
This project is funded out of Drainage Bond Fund 34
Recommended action
Staff recommends Council approval.