Title
Acceptance of completion of the Surface Water Treatment Plant Driveway Project.
Body
Summary:
The services of SKE Construction, LLC, through the Buy Board Cooperative Purchasing Program, was hired to perform the Water/Sewer Building Driveway Project for the amount of $29,945.46. The project consisted of installing a new driveway for the newly constructed maintenance building. The driveway has been completed and we are being billed for a lump sum cost of $29,945.46.
Fiscal/Budgetary Impact:
This project was budgeted in the Water/Sewer 2017-2018 fiscal year budget
Recommended action
Staff recommends accepting completion of this project and approval of the lump sum payment for the work performed.