File #: CHO 18-006    Version: 1 Name:
Type: Change Orders Status: Agenda Ready
File created: 11/13/2018 In control: City Council
On agenda: 12/4/2018 Final action:
Title: Acceptance of a change order on the New Animal Shelter construction.
Sponsors: Public Works
Attachments: 1. Change Proposal #22 -Revised Data Cabling
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Title

Acceptance of a change order on the New Animal Shelter construction.

Body

Summary:   The contract for the construction of the New Animal Shelter was awarded to Construction LTD in the amount of $2,240,668 there has been one change order issued back in October 2017 for $88,278.50 which brought the contract price to $2,328,966.50.

At this time we are requested an additional change order in the amount of $20,534.00 to cover the expense of network cabling for the new facility.  The network cabling was not included in the original contract. 

Approval of this, Change Order #2, will bring the total contract amount to $2,344,500.50.

Fiscal/Budgetary Impact:  This project is being funded out of Bond Fund 26.  There are sufficient funds in this account to cover this additional expense.

 

Recommended action

Staff recommends approval of Change Order #2