File #: AUT 18-119    Version: 1 Name:
Type: Authorization Status: Agenda Ready
File created: 12/6/2018 In control: City Council
On agenda: 12/18/2018 Final action:
Title: Authorization to reduce Tandem's retainage from 5% to 2% for the soccer fields.
Requester: Parks & Recreation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Title

Authorization to reduce Tandem’s retainage from 5% to 2% for the soccer fields.

 

Summary

Reducing the retainage amount from 5% to 2% permits the contractor to compensate all of his subcontractors due to inclement weather and project modifications. The 2% retainage will be held until close out and completion of the project.

 

Fiscal/Budgetary Impact

$3,325,655.65                                                               Total amount budgeted for project

$166,282.78                                                               5% Retainage from total amount budgeted for project

$66,513.11                                                               2% Retainage held until final close out and completion of project

 

Recommended Action

Authorize to reduce Tandem’s retainage from 5% to 2% for the soccer fields