File #: DIS 19-006    Version: 1 Name:
Type: Discussion Status: Agenda Ready
File created: 1/2/2019 In control: Deer Park Community Development Corporation
On agenda: 1/7/2019 Final action:
Title: Discussion of general conditions extended days and project cost for the Maxwell Adult Center.
Requester: Deer Park Community Development Corporation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Title

Discussion of general conditions extended days and project cost for the Maxwell Adult Center.

 

Summary

Due to changes from different elements from the project, the Department is requesting funds to be used from contingency and the unencumbered balance for the Maxwell Project to be used to pay for the extended days.

 

Fiscal/Budgetary Impact

                                          $38.000.00                     Cost for extended days                                          

                                          $11,186.27                     Contingency Funds

                                          $26,813.73                     Unencumbered Funds

                     

                                          $11,608.40                     Remaining unencumbered funds for Maxwell Adult Center

 

Recommended Action

Discussion only