Title
Acceptance and release of retainage for the 2nd Street Waterline Rehabilitation Project.
Body
Summary: SKE Construction, Inc. has completed the 2nd Street Waterline Rehabilitation Project and is now ready for Council acceptance and release of retainage. The project was completed in the amount of $142,768.49. The retainage for this project is $7,138.42. The project consisted of the rehabilitation of 6” waterline that runs down 2nd street to feed the WWTP. The old pipe had corroded and was causing pressure problems at the WWTP. This project was completed on time and in budget.
Fiscal/Budgetary Impact: This project was funded through Water and Sewer CIP funds.
Recommended action
Staff is requesting acceptance and retainage release for the completed project