Title
Authorization to seek bids for the fabrication of the Wastewater Plant clarifier launder covers.
Body
Summary:
On June 18, 2019 the council approved a contract with CDM Smith to develop specifications and bid documents to bid the fabrication of launder covers (weir covers) on the three clarifiers at the wastewater plant. The covers turned out to not be a sole source item so development of specifications and bid documents were required to bid the project. The estimated cost of fabrication and delivery of the covers is $200,000.
Fiscal/Budgetary Impact:
404-505-4904
Recommended action
Staff recommends council authorize bidding of the launder cover fabrication.