File #: ACT 20-022    Version: 1 Name:
Type: Acceptance Status: Agenda Ready
File created: 7/24/2020 In control: City Council
On agenda: 8/4/2020 Final action:
Title: Acceptance of completion and release of retainage for the 18" Force Main Rehabilitation Project Phase I.
Sponsors: Public Works
Requester: Public Works
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Title

Acceptance of completion and release of retainage for the 18” Force Main Rehabilitation Project Phase I.

 

Body

Summary:  Vaught Services has completed the 18” Force Main Rehabilitation Project and is now ready for Council acceptance and release of retainage.  The project was completed in the amount of $1,396,750.05.  The retainage for this project is $69,837.50.  The project consisted of the rehabilitation of the 18” Sanitary Sewer Force Main that runs from the South Plant on Luella.  This line transports over half of the City’s wastewater to the WWTP. This project was completed on time and in budget.

 

Fiscal/Budgetary Impact:  This project was funded through Water/Sewer Contingency funds.

 

Recommended action

Staff is requesting acceptance and retainage release for the completed project