Summary: Vaught Services has completed the 18” Force Main Rehabilitation Project and is now ready for Council acceptance and release of retainage. The project was completed in the amount of $1,396,750.05. The retainage for this project is $69,837.50. The project consisted of the rehabilitation of the 18” Sanitary Sewer Force Main that runs from the South Plant on Luella. This line transports over half of the City’s wastewater to the WWTP. This project was completed on time and in budget.
Fiscal/Budgetary Impact: This project was funded through Water/Sewer Contingency funds.
Recommended action
Staff is requesting acceptance and retainage release for the completed project