Title
Acceptance of completion of the 2020 Concrete Maintenance Project.
Body
Summary:
The project consisted of various concrete paving and sidewalk repairs throughout the City. The project was delayed several months due to Covid and is now ready to be accepted by Council and retainage release.
The project was awarded to Brooks Construction in the amount of $312,553.65. The project’s completed total cost is $228,963.45. The retainage to be released now that the project is concluded is $22,896.34. The project has been completed and is ready for Council acceptance.
Fiscal/Budgetary Impact:
This project was funded out of Street Maintenance Fund 4406
Recommended action
Staff is recommending that council accept completion of the project.