File #: ORD 21-085    Version: 1 Name:
Type: Ordinance Status: Agenda Ready
File created: 11/18/2021 In control: City Council
On agenda: 12/7/2021 Final action:
Title: Consideration of and action on an ordinance to amend the Fiscal Year 2021-2022 Budget for the Parks Maintenance Division for the Bridge Replacement in Dow Park.
Attachments: 1. Ord - Amend Budget FY22 Dow Park Bridges

Title

Consideration of and action on an ordinance to amend the Fiscal Year 2021-2022 Budget for the Parks Maintenance Division for the Bridge Replacement in Dow Park.

 

...Body

Summary: 

The Fiscal Year 2021-2022 budget for the Parks Maintenance Division includes $100,000.00 for the final phase of the bridge replacement in Dow Park.  These monies were budgeted to update and replace the final two pedestrian bridges, which are galvanized steel structures with concrete poured in place.  Because the actual cost of the final phase of this project exceeds the amount budgeted, a budget amendment in the amount of $30,000.00 is requested to appropriate the additional funds necessary to complete the project in Fiscal Year 2021-2022.  This additional appropriation would be funded by the current year’s contingency of the General Fund, which is available for this purpose.   

 

Fiscal Budget Impact: 

Add $30,000.00 to the Fiscal Year 2021-2022 budget for the Parks Maintenance Division (Account No. 010-432-49030, Improvements Other Than Buildings), to be funded by the General Fund contingency (Account No. 010-105-45100, Contingency), which is available for this purpose.

 

Recommended action

Approve the ordinance to amend the Fiscal Year 2021-2022 Budget for the Parks Maintenance Division for additional funds to complete the Bridge Replacement at Dow Park.